Nagaland Power Line Drawal Subsidy
Department of Industries & Commerce, Government of Nagaland · Central government
Nagaland reimburses 33/11KV power line costs up to Rs 10 lakh per industrial unit, once per unit.
Open, rolling. Applications are accepted continuously — there is no deadline.
Key facts
- Subsidy amount
- Up to ₹10,00,000
- Instrument
- Subsidy
- Deadline
- Rolling
- Disbursement
- Reimbursed after spend
About this scheme
Clause 6.7 of NTIIP 2025 tackles a genuine expense faced by factories set up at a distance from developed industrial zones: bringing grid power up to the gate. Where an eligible industrial unit lies outside the notified developed infrastructure and the Government has approved its location, the State refunds the expenditure incurred on drawing a 33/11KV line, capped at Rs 10.00 lakh.
The benefit is one-time in nature — a unit may claim it only once — and therefore it makes sense to seek it against the entire line-drawal cost instead of splitting the claim.
Who can apply
- Eligible business forms
- Not specified
- Udyam registration
- Not specified
- MSME registration
- Not specified
- DPIIT startup recognition
- Not required
- GST registration
- Not specified
- Where the business may be based
- Nagaland
- Industrial units in Nagaland that meet the eligibility criteria - The unit's location must fall outside the notified developed infrastructure - The Government must approve the location - A unit may avail this only once
How to apply
1. Secure the State Government's approval for the unit's location, either prior to starting the line-drawal work or at the same time as it. 2. Have the 33/11KV line drawn, and settle the cost with the power department or the contractor. 3. File an application with the Nagaland Department of Industries and Commerce as provided under clause 6.7 of the NTIIP. 4. Attach the estimate for the line-drawal cost, the paid bills, and the completion certificate issued by the electricity department.
How applications are assessed
Before any reimbursement is released, the Department carries out checks on three points: whether the unit falls outside the notified developed infrastructure, whether the location had Government approval, and whether the line-drawal cost is backed by documentation.
Frequently asked questions
What does the subsidy cover?
The expense of drawing a 33/11KV power line to the qualifying industrial unit is covered.
What is the ceiling?
Rs 10.00 lakh.
Can I claim it more than once?
No. An eligible unit can claim this subsidy only one time.
Does my unit's location matter?
Yes, provided the unit is situated outside the notified developed infrastructure and the Government has approved its location.
Sectors
- Nagaland
- Power Infrastructure
- Reimbursement
- Industrial Unit
- Ntiip 2025
Details last verified on 16 September 2026. Source: the issuer's published information.